OIG recommends that the Bureau of Near Eastern Affairs, in coordination with the Bureau of Administration, provide sufficient resources to the Contract Management Office-Frankfurt to ensure all unallowable costs are identified and recovered in a timely manner. This review should begin with those invoices provisionally approved beginning in September 2014 and already identified as awaiting post-payment review and then going back to identify and review those provisionally approved invoices submitted before September 2014 that did not receive full review.