Recommendation Contents
OIG recommends that the Bureau of Overseas Buildings Operations update its Policy and Procedures Directive for the Commissioning and Transition to Occupancy of Overseas Facilities (P&PD CM 01) to include procedures for identifying and approving instances in which it is appropriate to issue the certificate of substantial completion before commissioning has been fully completed. Specifically, these protocols should include mechanisms that (a) require a formal waiver be issued by the construction executive to proceed with substantial completion and occupancy even though commissioning is not yet complete, (b) establish milestones for completing the commissioning process after substantial completion and occupancy, and (c) execute a contract modification requiring the contractor to grant an extended warranty for those systems that were not commissioned at the time of substantial completion.