Recommendation Contents
OIG recommends that the Bureau of Overseas Buildings Operations update its Policy and Procedures Directive for the Commissioning and Transition to Occupancy of Overseas Facilities (P&PD CM 01) to require its project directors and facility managers to establish a memorandum of agreement 9 months prior to the estimated substantial completion target date to facilitate the building turnover process. This memorandum of agreement should, at a minimum, (a) define the type of access that Facility Management personnel and operations and management contractors should be given to new buildings prior to substantial completion; (b) specify relevant documentation, such as punch lists, lists of equipment to be maintained, and commissioning documentation that should be provided to facility managers and operations and management contractors; and (c) establish timelines for providing building access and documentation to facility personnel and operations and management contractors prior to substantial completion and occupancy.