Recommendation Contents
OIG recommends that the Bureau of Overseas Buildings Operations develop requirements mandating the use of a phased approach for projects that involve the construction of multiple buildings or facilities. This approach should outline specific phasing requirements for each building or facility constructed, including separate and distinctive commissioning, substantial completion, turnover, and acceptance requirements. This approach should also include protocols for a phased operations and management turnover process, requiring the contractor to provide key operations and management deliverables at the completion of each building if multiple buildings or facilities are being constructed under a single Bureau of Overseas Buildings Operations construction contract.