Recommendation Contents
OIG recommends that the Bureau of Administration, in coordination with the Bureau of Overseas Buildings Operations, take the following actions: (1) determine whether the questioned costs of $173,720, which were considered unallowable, for six requests for equitable adjustment for the New Embassy Compound Tegucigalpa, Honduras, construction contract (19AQMM19C0223) were allowable and (2) recover any costs determined to be unallowable, as shown in Table B.5.