Recommendation Contents
OIG recommends that the Bureau of Overseas Buildings Operations, in coordination with the Bureau of Administration and the Office of the Legal Advisor, a) determine whether and, if so, to what extent, the architecture-engineering firm Kieran-Timberlake PLC (under contract # SAQMMA-10-C-0060) is responsible for its design deficiencies resulting in $235,967 in additional costs expended to modify the new U.S. Embassy London semicircular pond and b) recover those costs for which the firm is determined to be liable.