Recommendation Contents
OIG recommends that the Bureau of Administration, in coordination with the Bureau of Overseas Buildings Operations (OBO), take the following actions: (1) determine whether the questioned costs of $725,509, which were considered to be unsupported, for request for equitable adjustment 003 for the New Consulate Compound Hyderabad, India, construction contract (SAQMMA16C0274), were supported and (2) recover any costs determined to be unsupported, as shown in Table B.6.