OIG recommends that the Bureau of Overseas Buildings Operations establish requirements in its Policy and Procedures Directive for the Commissioning and Transition to Occupancy of Overseas Facilities (P&PD CM 01) for the preparation and submission of key project documents for newly constructed facilities, including (a) owner’s project requirements, (b) a Basis of Design document, (c) systems manuals, (d) a commissioning plan, and (e) a final commissioning report. These documents should be prepared and submitted at the appropriate interval of construction for each building or facility constructed by the Bureau of Overseas Buildings Operations. Additionally, the requirements should indicate the parties responsible for preparation, review, and approval of each of the key project documents.