Management Assistance Report: Improvements Needed to the Security Certification Process To Ensure Compliance With Security Standards at Embassy Kabul, Afghanistan

AUD-MERO-17-28
    Report Contents
    Unclassified
    Unclassified
    Recommendation Number
    1
    Closed Implemented

    OIG recommends that the Bureau of Overseas Buildings Operations instruct Caddell Construction, Inc., to immediately replace the improperly altered security door components in accordance with contract terms and obtain confirmation from the Bureau of Diplomatic Security that the replaced components meet physical security standards.

    Recommendation Number
    2
    Closed Not Implemented Significant

    OIG recommends that the Bureau of Overseas Buildings Operations, in coordination with the Bureau of Diplomatic Security, revise the physical security certification process to include a follow-up inspection by DS to confirm that OBO took actions to address all identified deficiencies in accordance with physical security standards prior to occupancy.